Balancing hydropower development and ecological impacts in the Mekong: Tradeoffs for Sambor Mega Dam

Thomas B. Wild, Patrick M. Reed, Daniel P. Loucks, Martin Mallen-Cooper, Erland D. Jensen

    Research output: Contribution to journalArticle

    Abstract

    Home to one of the world's most biodiverse and productive freshwater fisheries, the Mekong River basin provides food and economic security to some 60 million people. The extensive hydropower development planned for the river basin has the potential to degrade this ecosystem. The basin's potentially most impactful and downstream-most proposed main stem dam, the 18-km-long Sambor Dam is to be located just upstream of critical nursery and fishery habitats of the Tonle Sap Lake and the Mekong Delta and just downstream of major spawning areas. We explore the potential to modify Sambor's siting, design, and operation (SDO) to balance hydropower and ecological outcomes. Our results demonstrate that there are opportunities to achieve more balanced ecology-energy outcomes. We use probabilistic seasonal measures of fish life cycle processes, energy production, and sediment passage to explore alternative SDO options. We consider both ecological concerns and energy production on equal footing prior to any power purchase agreements or fixed designs for Sambor, which is a first among any of the world's large dams. The Sambor Ecological Alternative (Sambor EA) dam considered in this study includes a combination of design and operational features to improve sediment and fish passage that do not exist at any of the world's large hydropower dams. Yet Sambor EA still poses a significant risk to the Mekong fishery and the millions who depend on it, given the appreciable uncertainty surrounding its potential ecological outcomes. Our results emphasize the need to address ecological concerns in advance of signing power purchase agreements that would otherwise limit the site-specific and integrated SDO modifications needed to achieve them. Our results also emphasize the importance of, and challenges in, carefully defining ecological performance measures and criteria, as well as the importance of carefully sampling reservoir operation possibilities.

    LanguageEnglish
    Article number05018019
    JournalJournal of Water Resources Planning and Management
    Volume145
    Issue number2
    DOIs
    Publication statusPublished - 01 Feb 2019

    Fingerprint

    hydropower
    ecological impact
    fishery
    Dams
    energy production
    dam
    Fisheries
    purchase
    river
    Catchments
    Fish
    Sediments
    life cycle
    river basin
    Rivers
    habitat
    ecology
    uncertainty
    food
    footing

    Cite this

    Wild, Thomas B. ; Reed, Patrick M. ; Loucks, Daniel P. ; Mallen-Cooper, Martin ; Jensen, Erland D. / Balancing hydropower development and ecological impacts in the Mekong : Tradeoffs for Sambor Mega Dam. In: Journal of Water Resources Planning and Management. 2019 ; Vol. 145, No. 2.
    @article{773a14ece3544087a4152ce29d8e789d,
    title = "Balancing hydropower development and ecological impacts in the Mekong: Tradeoffs for Sambor Mega Dam",
    abstract = "Home to one of the world's most biodiverse and productive freshwater fisheries, the Mekong River basin provides food and economic security to some 60 million people. The extensive hydropower development planned for the river basin has the potential to degrade this ecosystem. The basin's potentially most impactful and downstream-most proposed main stem dam, the 18-km-long Sambor Dam is to be located just upstream of critical nursery and fishery habitats of the Tonle Sap Lake and the Mekong Delta and just downstream of major spawning areas. We explore the potential to modify Sambor's siting, design, and operation (SDO) to balance hydropower and ecological outcomes. Our results demonstrate that there are opportunities to achieve more balanced ecology-energy outcomes. We use probabilistic seasonal measures of fish life cycle processes, energy production, and sediment passage to explore alternative SDO options. We consider both ecological concerns and energy production on equal footing prior to any power purchase agreements or fixed designs for Sambor, which is a first among any of the world's large dams. The Sambor Ecological Alternative (Sambor EA) dam considered in this study includes a combination of design and operational features to improve sediment and fish passage that do not exist at any of the world's large hydropower dams. Yet Sambor EA still poses a significant risk to the Mekong fishery and the millions who depend on it, given the appreciable uncertainty surrounding its potential ecological outcomes. Our results emphasize the need to address ecological concerns in advance of signing power purchase agreements that would otherwise limit the site-specific and integrated SDO modifications needed to achieve them. Our results also emphasize the importance of, and challenges in, carefully defining ecological performance measures and criteria, as well as the importance of carefully sampling reservoir operation possibilities.",
    keywords = "Ecology, Hydropower planning, Sustainable development",
    author = "Wild, {Thomas B.} and Reed, {Patrick M.} and Loucks, {Daniel P.} and Martin Mallen-Cooper and Jensen, {Erland D.}",
    year = "2019",
    month = "2",
    day = "1",
    doi = "10.1061/(ASCE)WR.1943-5452.0001036",
    language = "English",
    volume = "145",
    journal = "Journal of Water Resources Planning and Management",
    issn = "0733-9496",
    publisher = "American Society of Civil Engineers (ASCE)",
    number = "2",

    }

    Balancing hydropower development and ecological impacts in the Mekong : Tradeoffs for Sambor Mega Dam. / Wild, Thomas B.; Reed, Patrick M.; Loucks, Daniel P.; Mallen-Cooper, Martin; Jensen, Erland D.

    In: Journal of Water Resources Planning and Management, Vol. 145, No. 2, 05018019, 01.02.2019.

    Research output: Contribution to journalArticle

    TY - JOUR

    T1 - Balancing hydropower development and ecological impacts in the Mekong

    T2 - Journal of Water Resources Planning and Management

    AU - Wild, Thomas B.

    AU - Reed, Patrick M.

    AU - Loucks, Daniel P.

    AU - Mallen-Cooper, Martin

    AU - Jensen, Erland D.

    PY - 2019/2/1

    Y1 - 2019/2/1

    N2 - Home to one of the world's most biodiverse and productive freshwater fisheries, the Mekong River basin provides food and economic security to some 60 million people. The extensive hydropower development planned for the river basin has the potential to degrade this ecosystem. The basin's potentially most impactful and downstream-most proposed main stem dam, the 18-km-long Sambor Dam is to be located just upstream of critical nursery and fishery habitats of the Tonle Sap Lake and the Mekong Delta and just downstream of major spawning areas. We explore the potential to modify Sambor's siting, design, and operation (SDO) to balance hydropower and ecological outcomes. Our results demonstrate that there are opportunities to achieve more balanced ecology-energy outcomes. We use probabilistic seasonal measures of fish life cycle processes, energy production, and sediment passage to explore alternative SDO options. We consider both ecological concerns and energy production on equal footing prior to any power purchase agreements or fixed designs for Sambor, which is a first among any of the world's large dams. The Sambor Ecological Alternative (Sambor EA) dam considered in this study includes a combination of design and operational features to improve sediment and fish passage that do not exist at any of the world's large hydropower dams. Yet Sambor EA still poses a significant risk to the Mekong fishery and the millions who depend on it, given the appreciable uncertainty surrounding its potential ecological outcomes. Our results emphasize the need to address ecological concerns in advance of signing power purchase agreements that would otherwise limit the site-specific and integrated SDO modifications needed to achieve them. Our results also emphasize the importance of, and challenges in, carefully defining ecological performance measures and criteria, as well as the importance of carefully sampling reservoir operation possibilities.

    AB - Home to one of the world's most biodiverse and productive freshwater fisheries, the Mekong River basin provides food and economic security to some 60 million people. The extensive hydropower development planned for the river basin has the potential to degrade this ecosystem. The basin's potentially most impactful and downstream-most proposed main stem dam, the 18-km-long Sambor Dam is to be located just upstream of critical nursery and fishery habitats of the Tonle Sap Lake and the Mekong Delta and just downstream of major spawning areas. We explore the potential to modify Sambor's siting, design, and operation (SDO) to balance hydropower and ecological outcomes. Our results demonstrate that there are opportunities to achieve more balanced ecology-energy outcomes. We use probabilistic seasonal measures of fish life cycle processes, energy production, and sediment passage to explore alternative SDO options. We consider both ecological concerns and energy production on equal footing prior to any power purchase agreements or fixed designs for Sambor, which is a first among any of the world's large dams. The Sambor Ecological Alternative (Sambor EA) dam considered in this study includes a combination of design and operational features to improve sediment and fish passage that do not exist at any of the world's large hydropower dams. Yet Sambor EA still poses a significant risk to the Mekong fishery and the millions who depend on it, given the appreciable uncertainty surrounding its potential ecological outcomes. Our results emphasize the need to address ecological concerns in advance of signing power purchase agreements that would otherwise limit the site-specific and integrated SDO modifications needed to achieve them. Our results also emphasize the importance of, and challenges in, carefully defining ecological performance measures and criteria, as well as the importance of carefully sampling reservoir operation possibilities.

    KW - Ecology

    KW - Hydropower planning

    KW - Sustainable development

    UR - http://www.scopus.com/inward/record.url?scp=85058160593&partnerID=8YFLogxK

    UR - http://www.scopus.com/inward/citedby.url?scp=85058160593&partnerID=8YFLogxK

    U2 - 10.1061/(ASCE)WR.1943-5452.0001036

    DO - 10.1061/(ASCE)WR.1943-5452.0001036

    M3 - Article

    VL - 145

    JO - Journal of Water Resources Planning and Management

    JF - Journal of Water Resources Planning and Management

    SN - 0733-9496

    IS - 2

    M1 - 05018019

    ER -